• BRAC Banner
  • BRAC Renovation Project
    (Tentatively begins April 1 and will be completed January 2021)

  • Programs and activities will continue through construction. Staff will communicate to program participants regarding potential modifications during construction.

  • As responsible stewards of your tax dollars, we have developed a schedule and plan for the renovation of the Bolingbrook Recreation & Aquatic Complex that you entrusted us with during the 2018 referendum ask. This project includes the following items.

    This project includes the following items:

    • Renovated Main Entrance
    • New Program Space
    • Five New Family Changing Rooms
    • Renovated Fitness and Aquatic Locker Rooms

    We have developed a schedule that will minimize disruption of park district programming. We appreciate your patience as we work through this project and we urge all residents to visit our website and regularly follow us on social media (Facebook, Twitter and Instagram) to stay up-to-date on our progress and of any changes in the timeline below.

  • BRAC Layout
  • Tentative BRAC Construction Timeline: Phase 1 (April 1-June 1)
    Fencing installedSite demolition begins
    Underground / Concrete work for additionRoof work begins
    Tiling of floor beginsEnclosing of the new entrance
    Updated lobby atrium seating installed-
  • Tentative BRAC Construction Timeline: Phase 2 (June 1-December 1)
    Demolition of locker room and indoor pool officesUnderground plumbing and electric work for addition and locker rooms
    Steel, masonry, and drywall work for additionRoofing for both existing and addition
    Storm sewer for additionHVAC for addition and pool offices installed
    Plumbing for addition and locker roomsCeramic tile and interior finishes for addition / locker rooms
    Landscaping and finish site work-
  • Tentative BRAC Construction Timeline: Phase 3 (November 1-January 1, 2021)
    Finish workFencing removed
    Furniture, fixtures, and equipment installed-